Contract A
I-10 from Harris/Fort Bend County Line to East of Peek Road (SH 99)
Bid Amount $83 Million
Total Project Duration 921 days
Incentives/Disincentives
| Milestone |
Milestone Duration (Days) * |
Max. Days Allowed for Early Completion |
Daily
Incentive Amount |
Daily
Disincentive Amount |
Milestone Started |
Milestone Completed |
Monetary Value |
Milestone 1: Close/reopen partial SH 99 frontage road underpass. |
37 |
10 |
($50,000 per day for 10 days)
Maximum $500,000 |
($50,000 per day) |
02/11/2005 |
03/03/2005 |
$500,000** |
Milestone 2: Beginning of project to opening of SH 99 underpass and I-10 U-turns; cross-traffic on SH 99 in final configuration and detour for Mason Rd closure completed. |
628 |
0 |
N/A |
($20,000 per day) |
09/18/2003 |
07/07/2005 |
N/A |
Milestone 3: Westbound mainlanes traffic shift to proposed pavement throughout project limits. |
821 |
100 |
($25,000 per day for 100 days)
Maximum $2,500,000 |
($20,000 per day) |
09/18/2003 |
12/17/2005 |
$2,500,000**
|
Milestone 4: Final Acceptance; Traffic in final configuration. |
921 |
0 |
N/A |
($5,000 per day) |
09/18/2003 |
11/20/2006 |
N/A |
* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.
|