Contract B Incentives/Disincentives
underline image

Contract B

I-10 East of Grand Parkway to West of SH 6
Bid Amount $208 Million
Total Project Duration 930 days

Incentives/Disincentives
Milestone Milestone Duration (Days) * Max. Days Allowed for Early Completion Daily Incentive Amount Daily disincentive Amount Milestone Started Milestone Completed Monetary Value

Milestone 1: Overall project completion.

930

0

N/A

($5,000 per day)

06/10/2003

 

 

Milestone 2: Completion of I-10 mainlanes over N. Westgreen and S. Greenhouse.

173

30

($15,000 per day for 30 days)
Maximum $450,000

($15,000 per day)

02/18/2004

07/31/2004

$450,000**

Milestone 3: Completion of I-10 mainlanes over Fry Rd. and Park Ten Blvd.

234

30

($10,000 per day for 30 days)
Maximum $300,000

($5,000 per day)

10/11/2004

06/06/2005

$300,000**

Milestone 3A*: Closure/Reopening of I-10 cross street at Fry Road

109

30

($50,000 per day for 30 days)
Maximum $1,500,000

($50,000 per day)

01/11/2005

03/25/2005

$1,500,000**

Milestone 4: Completion of I-10 mainlanes over Mason Rd. and Barker-Cypress Rd.

195

30

($10,000 per day for 30 days)
Maximum $300,000

($5,000 per day)

09/06/2005

03/17/2006

$300,000**

Milestone 4A*: Close/Reopen
I-10 cross street at Mason Rd.

105

30

($50,000 per day for 30 days)
Maximum $1,500,000

($40,000 per day)

11/01/2005

01/13/2006

$1,500,000**

Milestone 4B*: Close/Reopen
I-10 cross street at Barker Cypress.

88

30

($50,000 per day for 30 days)
Maximum $1,500,000

($30,000 per day)

11/18/2005

01/24/2006

$1,500,000**

* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.