Contract C1 Incentives/Disincentives
underline image

Contract C1

From West of SH 6 to East of Eldridge on IH 10
Bid Amount $153 Million
Total Project Duration 1,167 days

Incentives/Disincentives
Milestone Milestone Duration (Days) * Max. Days Allowed for Early Completion Daily Incentive Amount Daily Disincentive Amount Milestone Started Milestone Completed Monetary Value

Milestone 1: Complete new I-10 westbound frontage road and switch traffic.

323

20

($10,000 per day for 20 days)
Maximum $200,000

($10,000 per day)

05/02/2005

04/10/2006

$200,000**

Milestone 2: Complete all westbound mainlane work necessary for transition to the new I-10 westbound mainlanes.

230

90

($10,000 per day for 90 days)
Maximum $900,000

($10,000 per day)

04/10/2006

08/19/2006

$900,000**

Milestone 3: Complete all mainlane work necessary to switch the HOV to the proposed location.

178

0

NA

($10,000 per day)

08/21/2006

03/11/2007

N/A

Milestone 4: Complete all eastbound mainlane work necessary for transition to the new I-10 eastbound mainlanes.

182

30

($10,000 per day for 30 days)
Maximum $300,000

($10,000 per day)

03/13/2007

08/04/2007

$300,000^^

Milestone 5: Complete all final striping on the mainlane and frontage.

309

60

($30,000 per day for 60 days)
Maximum $1,800,000

($30,000 per day)

08/29/2007

Target Date 05/28/2008

 

Milestone 6: Administrative work to close out project.

1239

0

NA

($1,650 per day)

05/02/2005

Target Date 03/29/2009

 

Milestone 7: Complete all work necessary for opening of the temporary SH 6 intersection.

9

6

($50,000 per day for 6 days)
Maximum $300,000

($50,000 per day)

09/15/2005

09/18/2005

$300,000**

Milestone 8: Complete all work necessary for opening of the temporary Eldridge intersection.

9

6

($50,000 per day for 6 days)
Maximum $300,000

($50,000 per day)

04/07/2006

04/09/2006

$300,000**

Milestone 9: Complete all work for necessary to open METRO/Tollway Lanes.

26

0

NA

($5,000 per day)

03/13/2007

04/07/2007

N/A

Milestone 10: Completion of SH 6 mianlanes and frontages.

551

120

($10,000 per day for 120 days)
Maximum $1,200,000

($10,000 per day)

04/02/2007

Target Date 12/23/2008

 

Early completion

7/31/2008

 

$2,500,000

 

 


* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.