Contract D Incentives/Disincentives
underline image

Contract D

I-10, East of Beltway 8 to East of Kirkwood
Bid Amount $250 Million
Total Project Duration 1351 days

Incentives/Disincentives
Milestone Milestone Duration (Days) * Max. Days Allowed for Early Completion Daily Incentive Amount Daily disincentive Amount Milestone Started Milestone Completed Monetary Value

Milestone 1: Traffic shift of I-10 westbound mainlane traffic to the completed westbound mainlane pavement.

307

20

($30,000 per day for 20 days)
Maximum $600,000

($30,000 per day)

10/04/2004

07/31/2005

$600,000**

Milestone 2: Traffic shift of the I-10 METRO HOV lane from existing location to completed westbound mainlane pavement.

178

20

($10,000 per day for 20 days)
Maximum $200,000

($10,000 per day)

08/01/2005

12/18/2005

$200,000**

Milestone 3: Traffic shift of the I-10 eastbound mainlane to the completed median.

149

20

($30,000 per day for 20 days)
Maximum $600,000

($30,000 per day)

12/19/2005

03/19/2006

$600,000**

Milestone 4: Completion of all the work as shown on phase 5-4 west of BW8.

232

60

($30,000 per day for 60 days)
Maximum $1,800,000

($30,000 per day)

04/03/2006

09/30/2006

$1,800,000**

Milestone 5: Opening of the Beltway 8 northbound and southbound flyovers bridges and approaches, including auxiliary lanes, shoulders, in their final configuration.

404

60

($10,000 per day for 60 days)
Maximum $600,000

($10,000 per day)

05/04/2005

06/27/2007

$600,000**

Milestone 6: Opening of I-10 eastbound and westbound mainlanes including auxiliary lanes and shoulders in the final configuration.

86

25

($20,000 per day for 25 days)
Maximum $500,000

($20,000 per day)

 

 

 

Milestone 7: Final inspection and acceptance of the project.

1401

0

N/A

 

10/04/2004

Target Date
01/14/2009

 

Milestone H: Reopen Connector H to traffic.

97

30

($10,000 per day for 30 days)
Maximum $300,000

($10,000 per day)

04/07/2007

06/21/2007

$300,000**

Milestone A: Reopen Connector A to traffic.

219

60

($20,000 per day for 60 days)
Maximum $1,200,000

($20,000 per day)

04/07/2007

09/18/2007

$1,200,000**

Milestone G: Reopen Connector G to traffic.

204

60

($10,000 per day for 60 days)
Maximum $600,000

($10,000 per day)

04/20/2007

12/01/2007

$600,000**

Milestone B: Reopen Connector B to traffic.

90

30

($10,000 per day for 30 days)
Maximum $300,000

($10,000 per day)

10/05/2007

12/07/2007

$300,000**

Milestone E: Reopen Connector E to traffic.

78

30

($10,000 per day for 30 days)
Maximum $300,000

($10,000 per day)

01/05/2008

 

 

Milestone D: Reopen Connector D to traffic.

196

60

($20,000 per day for 60 days)
Maximum $1,200,000

($20,000 per day)

01/05/2008

Target Date
06/05/2008

 

Milestone F: Reopen Connector F to traffic.

204

60

($20,000 per day for 60 days)
Maximum $1,200,000

($20,000 per day)

 

 

 

Milestone C: Reopen Connector C to traffic.

117

45

($10,000 per day for 45 days)
Maximum $450,000

($10,000 per day)

 

 

 

* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.