Contract G Incentives/Disincentives
underline image

Contract G

East of IH 610 to West of Washington
Bid Amount $43 Million
Total Project Duration 438 days

Incentives/Disincentives
Milestone Milestone Duration (Days) * Max. Days Allowed for Early Completion Daily Incentive Amount Daily Disincentive Amount Milestone Started Milestone Completed Monetary Value

Milestone 1: Construction of temporary Union Pacific Railroad bridge.

162

0

NA

($30,000 per day)

03/05/2007

09/23/2007

NA

Milestone 2: Traffic shift of I-10 eastbound and westbound mainlanes to their final configuration.

251

30

($30,000 per day for 30 days)
Maximum $900,000

($30,000 per day)

10/22/2007

Target Date 07/07/2008

 

Milestone 3: Administrative milestone from start of project to final completion.

438

0

NA

($2,000 per day)

03/05/2007

Target Date 08/06/2008

 

Interim Milestone A: Construction of permanent Union Pacific Railroad bridge.

96

0

NA

($30,000 per day)

10/22/2007

02/08/2008

NA

Interim Milestone B: Closure and reopening of the eastbound entrance ramp from Washington.

47

20

($5,000 per day for 20 days)
Maximum $100,000

($5,000 per day)

 

 

 

* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.