Contract C1
underline image

Contract C1 Summary

  • Reconstruction of 2.27 Miles of I-10, East of Eldridge to West of SH 6
    (includes the construction of SH 6 lanes over I-10)
  • Reconstruction of an Eight to Ten-lane Divided Urban Freeway Facility
  • Reconstruction of 8 Entrance/Exit Ramps and 10 Bridges
  • Reconstruction of 2 Grade Separated Intersections at SH 6 and Eldridge
  • $153 Million Low Bid Received March 8, 2005
    • Contract awarded to Williams Brothers Construction Company
  • 44 Months Duration (May 2005 to December 2008)
  • Construction Officially Began May 2, 2005
  • Traffic Requirements During Construction
    • Maintain Existing Number of Mainlanes during Peak Periods
    • Maintain Local Access Across Corridor
    • Maintain Existing HOV in Operation
    • Maintain Current ITS Operations
      • Variable Message Signs, Cameras, Ramp Meters, etc.
  • Incentives/Disincentives
  • Click here for before/after renderings of Katy Freeway at SH 6

Image of Katy Freeway Contract C1 Construction
Click here for Contract C1
construction photos.

Contract C1 Phasing Timeline

Top Bar of Graphic

Phase I

Graphic of Contract C1 Phase 1 Timeline

Phase II

Graphic of Contract C1 Phase 2 Timeline

Phase III

Graphic of Contract C1 Phase 3 Timeline

Phase IV

Graphic of Contract C1 Phase 4 Timeline

 

Bottom Bar of Graphic