Contract C2 Summary
- Reconstruction of 1.8 miles of I-10, East of Kirkwood to East of Eldridge
- Reconstruction of an Eight to Ten-lane Divided Urban Freeway Facility
- Reconstruction of 8 Entrance/Exit Ramps and 4 Bridges
- Reconstruction of 2 Grade Separated Intersections at Dairy Ashford and Kirkwood
- 41 Months Duration (March 2005 to October 2008)
- Construction Officially Began April 4, 2005
- $84 Million Low Bid Received December 8, 2004
- Contract awarded to Balfour-Beatty Construction
- Traffic Requirements During Construction
- Maintain Existing Number of Mainlanes during Peak Periods
- Maintain Local Access Across Corridor
- Maintain Existing HOV in Operation
- Maintain Current ITS Operations
- Variable Message Signs, Cameras, Ramp Meters, etc.
- Incentives/Disincentives
|