Contract D
underline image

Contract D Summary

  • I-10, East of Beltway 8 to East of Kirkwood
  • Reconstruction of 1.99 Miles to an Eight to Ten-Lane Divided Urban Freeway Facility
  • Reconstruction of 14 Bridges/Connectors
  • 51 Months Duration
  • $250 Million Low Bid Received July 8, 2004
    • Contract awarded to Williams Brothers Construction Company
  • Construction Officially Began August 2004
    • First 2 Years of Construction will be Dedicated to I-10 Main Lanes Expansion
    • Construction of the Beltway 8 Direct Connectors will Begin January 2007
  • Traffic Requirements During Construction
    • Maintain Existing Number of Mainlanes during Peak Periods
    • Maintain Local Access Across Corridor
    • Maintain Existing HOV in Operation
    • Maintain Current ITS Operations
      • Variable Message Signs, Cameras, Ramp Meters, etc.
    • Direct Connectors will be Closed Two at a Time with Accelerated Construction Required to Minimize Downtime
  • Link to Incentives/Disincentives
  • Click Here for Before/After Renderings of Katy Freeway at Beltway 8.

Image of Katy Freeway Contract D Construction
Click here for Contract D
construction photos.

Contract D Phasing Timeline

    Green Area represents where we are now.

Top Bar of Graphic

Phase I

Graphic of Contract D Phase 1 Timeline

Phase II

Graphic of Contract D Phase 2 Timeline

Phase III

Graphic of Contract D Phase 3 Timeline

Phase IV

Graphic of Contract D Phase 4 Timeline

Phase V

Graphic of Contract D Phase 5 Timeline

Phase VI

Graphic of Contract D Phase 6 Timeline

Phase VII

Graphic of Contract D Phase 7 Timeline
Bottom Bar of Graphic

 



Contract D Incentives

  • Milestones for Direct Connectors Closures
  • Major Milestones for Phase Transitions
  • Project Conclusion Milestone
  • Maximum Amount for Early Completion
    • Contract D - $13.3 Million

Contract D Disincentives

  • Liquidated Damages
    • Milestones for Direct Connectors Closures
    • Major Milestones for Phase Transitions
    • Project Conclusion (substantial completion)

  • Per/Day Penalties
    • Contract D - $5,000 to $75,000