Contract E1 Summary
- Reconstruction of 2.65 Miles I-10, East of Campbell to east of Beltway 8
- Reconstruction of an Eight to Ten-lane Divided Urban Freeway Facility
- Reconstruction of 14 Entrance/Exit Ramps and 12 Bridges
- Reconstruction of 4 Grade Separated Intersections at Gessner, Bunker Hill, Blalock/Echo Lane and Campbell
- $204 Million Low Bid Received January 27, 2005
- Contract awarded to Williams Brothers Construction Company
- 44 Months Duration (February 2005 to October 2008)
- Construction Officially Began March 1, 2005
- Traffic Requirements During Construction
- Maintain Existing Number of Mainlanes during Peak Periods
- Maintain Local Access Across Corridor
- Maintain Existing HOV in Operation
- Maintain Current ITS Operations
- Variable Message Signs, Cameras, Ramp Meters, etc.
- Incentives/Disincentives
|