Contract F
underline image

Contract F Summary

  • I-10/I-610 Interchange and I-610 from South of Post Oak Blvd. to North of Old Katy Road
  • Reconstruction of 1.08 miles along I-10 and 2.55 miles along I-610
  • Total Reconstruction of the 4 Level Directional Interchange
  • Reconstruction of 14 Structures
    • Including Bridge Structures at Post Oak, Woodway, Memorial, Buffalo Bayou
  • 51 Months Duration
  • $263 Million Low Bid Received July 1, 2003
    • Contract awarded to Williams Brothers Construction Company
  • Construction Officially Began October 1, 2003
  • Traffic Requirements During Construction
    • Maintain Existing Number of Mainlanes during Peak Periods
    • Maintain Local Access Across Corridor
    • Maintain Existing HOV in Operation
    • Maintain Current ITS Operations
      • Variable Message Signs, Cameras, Ramp Meters, etc.
  • Incentives/Disincentives

Image of Katy Freeway Contract F Construction
Click here for Contract F
construction photos.

Contract F Phasing Timeline


I-10

     Green Area represents where we are now.

Top Bar of Graphic

Phase I

Graphic of Contract F I-10 Phase 1 Timeline

Phase II

Graphic of Contract F I-10 Phase 2 Timeline

Phase III

Graphic of Contract F I-10 Phase 3 Timeline

Phase IV

Graphic of Contract F I-10 Phase 4 Timeline

 

Bottom Bar of Graphic

I-610

     Green Area represents where we are now.

Top Bar of Graphic

Phase I

Graphic of Contract F I-610 Phase 1 Timeline

Phase II

Graphic of Contract F I-610 Phase 2 Timeline

Phase III

Graphic of Contract F I-610 Phase 3 Timeline

Phase IV

Graphic of Contract F I-610 Phase 4 Timeline

Phase V

Graphic of Contract F I-610 Phase 5 Timeline

 

Bottom Bar of Graphic
 

Contract F Typical Construction Phasing

 

Click here to view a detailed graphic of typical mainlane construction for Contract F, using I-10

 

 

 

 

 

 


 

Link to Contract F I-10 Typical Mainlane Construction Sequence Page
   

Click here to view a detailed graphic of typical mainlane construction for Contract F, using I-610

Small Image of I-610 Typical Mainlane Construction Sequence for Contract F


Contract F Incentives

  • Interim Milestones
  • Major Milestones for Phase Transitions
  • Project Conclusion Milestone
  • Maximum Amount for Early Completion
    • Contract F - $11.7 Million

Contract F Disincentives

  • Liquidated Damages
    • Interim Milestones
    • Major Milestones at End of Each Phase
    • Project Conclusion (substantial completion)
  • Per/Day Penalties
    • Contract F - $5,000 to $75,000