Contract B Construction Photos
underline image

Click photo for larger image.
January 2005

Construction of embankment the I-10 mainlanes at Park Ten (along the I-10 eastbound frontage road).

The new Fry Road intersection at the I-10 eastbound frontage road is nearing completion (looking south).

Construction crews are removing the existing Fry Road bridge over I-10.

Overview of the remaining portion of the existing Fry Road bridge over I-10 before its removal.

Within a month of closing the Fry Road bridge over I-10, traffic was switched onto new the I-10 westbound mainlanes over Fry Road. (WB has a total of 109 days to completely open the new Fry Road intersection.)

 

Construction Photos
Click for previous image.       Click for next image.

Image of Katy Freeway Contract B January 2005 Construction



[Katy Freeway [Program Overview] [Program Timeline] [Newsroom] [Lane Closures] [FAQs] [Feedback] [Sitemap]

Image: TxDOT Logo and Copyright 2007