Fast Facts
Reconstruction of 23 Miles of Interstate Freeway
Reconstruction of 2 Freeway-Freeway Interchanges
Reconstruction of 27 Grade Separated Intersections
Construction Period Spans 2003 - 2009
Total Projected Cost $2.7 Billion
Construction Cost $1.7 Billion
ROW Acquisition, Relocation Assistance and Utility Relocation Cost $705 Million
Primary Funding for the Program is from Federal Highway Administration (FHWA) and Texas Department of Transportation (TxDOT) with $250 Million from Harris County for the Construction of the Toll Lanes
Construction started June 2003
Program will be Constructed in 9 Construction Contracts
Last Revison May 31, 2005